- The IDIQ covers in-situ thermal treatment and chemical oxidation
- Work runs through November 2031 at the Pensacola site
- The Escambia site was included in the National Priorities List
Parsons has won a $45.7 million U.S. Army Corps of Engineers contract to treat contaminated groundwater beneath the Escambia Wood Treating Co. Superfund site in Pensacola, Florida, using in situ thermal treatment and in situ chemical oxidation.
The firm-fixed-price, indefinite-delivery/indefinite-quantity award to Parsons Government Services drew two bids solicited over the internet, the Department of War said Thursday. Work locations and funding will be set with each order, with an estimated completion date of Nov. 18, 2031.
The award covers the site’s second operable unit, which addresses groundwater. Soil remediation was handled separately and completed in 2010, Inside Climate News reported.
What Contaminated the Escambia Wood Site?
The Escambia site pressure-treated utility poles, foundation pilings and lumber from 1942 until it closed in 1982. It treated wood with coal-tar creosote until roughly 1970 and introduced pentachlorophenol dissolved in No. 6 diesel fuel in 1963, according to the Environmental Protection Agency. From 1970 to 1982, pentachlorophenol served as the site’s only preservative. Wastewater ponds and surface impoundments, several of them unlined, were the primary route by which those chemicals reached the aquifer.
EPA excavated roughly 225,000 cubic yards of contaminated soil in a 1991 and 1992 removal action, stockpiling it onsite under a secure cover — the mound local residents came to call Mount Dioxin. The agency added the site to the National Priorities List in December 1994 and later relocated more than 400 households from surrounding neighborhoods, making it one of the largest permanent relocations in Superfund history.
Escambia filed for bankruptcy and abandoned the property in 1991, leaving the cleanup to the federal program, with Florida covering a 10 percent state share of remedial action costs.
What Does the Groundwater Remedy Address?
Naphthalene is the principal contaminant and the marker EPA uses to map the plume, which extends roughly a mile and a half east-southeast from the site toward Bayou Texar across three zones of the sand and gravel aquifer. Concentrations in the source area ran high enough to indicate dense non-aqueous phase liquid, which EPA classified as a principal threat waste.
The 2008 record of decision divided the plume by concentration and assigned a technology to each: chemical oxidation paired with enhanced bioremediation in the source area, enhanced bioremediation in the high-concentration zone, and monitored natural attenuation in the dilute portion. Cleanup levels cover eight site-wide contaminants, including naphthalene, benzene, pentachlorophenol and carbazole, with the goal of restoring the aquifer to beneficial use.
How Is the Escambia Cleanup Funded?
EPA allocated $40 million for groundwater work from the Infrastructure Investment and Jobs Act, as part of a $1 billion Superfund investment the agency announced in December 2021.
The agency has spent roughly $140 million on the soil remedy, according to a 2024 EPA inspector general report. That report found fencing and signage around the site in poor condition and institutional controls barring residential use going unenforced, and warned that the groundwater work would be at risk if those conditions persisted.
The Escambia Wood property now belongs to Escambia County.